East Side Light Rail Time & Budget

 

Table created from data in :

STUDY SAYS MAX CALCULATIONS WERE WRONG , The Oregonian December 29, 1989

Pickrell Report mentioned in the Oregonian article  (with OCR text)

Trimet’s claim:

“The 15-mile Eastside MAX line opened in 1986, stretching east from downtown Portland to Gresham. The project was completed on time and under budget. “ (bold added)

 

Above is from Trimet's FactSheet

 

 

1978  Forecast

1990 Actual

1986

Ridership

42,500

19,700

54% under ridership projection

cost of MAX

$172 million

$266 million

55% over construction budget

operating costs for MAX

$3.8 million

$5.8 million

53% over  operating budget

opening date

1983

1986

3 years late